Bangabandhu Sheikh Mujid Railway Bridge Construction Project Package – WD2
(Western Part of Civil Works), Bangladesh
2023 |
|
- Proof Stress Tensile & Elongation Test
- Modulus Elasticity Test
- Relaxation Test
- PC Dust Dimension, Wall Thickness & Tolerance Test
- Galvanized Zinc Coating Thickness Test
|
| North–South Commuter Railway Extension (NSCR-Ex) Project, Philippines
2023 |
- Italian-Thai Development Public Company Limited
|
- Creep Test
- Cylinder Test
- Static Modulus Elasticity Test
|
| FIP Testing for HM-120SC Segmental Construction Adhesive
2022 |
- Shanghai Horse Construction Co. Ltd.
|
- Gel Time (Pot-Life) Test
- Open Time Test
- Sag Flow Test
- Angle of International Friction (Squeezeability) Test
- Shrinkage Test
- Water Absorption and Solubility Test
- Heat Resistance Test
- Compressive Strength Test
- Instantaneous and Defered Modulus Test
- Tensile Bending Strength (MOR) Test
- Slant Shear Bonding Test
- Shear Modulus Test
|
Blue Sea Daian, China Project
2022
|
- JEKS ENGINEERING PTE. LTD
|
- Cement Content Test
- Original Water Content Test
- Cement Aggregate Content Test
- Chemical Composition Analysis (Cement, Fine and Coarse Aggregate)
|
Polymer Matric Composite Materials / Fibre Plate, India
2022 – 2023
|
- The Bhor Chemicals And Plastic Pvt. Ltd.
|
- Tensile Strength Test
- Elongation Test
- Tensile Modulus Test
|
Precast Segmental Girders for North–South Commuter Railway Project, Philippines
2021
|
|
- Slag Flow Test
- Gel Time Test
- Open Time Test
- Three-Point Tensile Bending Test
- Compressive Strength Test
- Heat Resistance Test
- Slant Shear Bonding Test
|
Sikafloor 21 Purcem LP Properties Test, Indonesia
2021
|
|
- Abrasion Resistance Test
- Coefficient of Friction Test
- Coefficient of Thermal Expansion Test
- Flexural Strength and Modulus Test
- Impact Resistance Test
- Identiation Hardness Test
- Resistance to Thermal Shock Test
- Sensory Evaluation Test
- Water Absorption Test
|
PHM North SISI, Indonesia
2021
|
- OAG Offshore Pipeline Services Sdn Bhd
|
- Compressive Strength Test
|
HKPM, Hong Kong
2021
|
- Green Arck Precast Sdn Bhd
|
|
North–South Commuter Railway (NSCR) Project, Philippines Package CP01 (MalolosTutuban) – Elevated Structures, 6 Stations and Depot
2021 – 2023
|
- Taisei – DMCI Joint Venture
|
- Creep Test
- Drying Shrinkage Test
- Modulus Test
- RCPT Test
|
Concrete Protective Coating of Taiwan Highway Projects, Taiwan
2021
|
|
- Behavior after Artificial Weathering Test
- Bonding Strength Test
- Carbon Dioxide Permeability Test
- Crack Bridging Test
- Liquid Water Permeability Test
- Water Vapour Transmission Test
|
Bukit Tun Phase Development, Indonesia
2020 – 2021
|
- OAG Offshore Pipeline Service Sdn Bhd
|
- Thermal Conductivity Test
- Tensile & Elongation Test for Moulding Plastic
|
CMC, Sri Lanka
2019 – 2023
|
|
- Jacking Pipe Test
- Liquid Penetration Inspection Test
|
MRT 7, Philippines
2018
|
|
|
La Pampilla, Peru Project
2018 – 2019
|
- OAG Offshore Pipeline Service Sdn Bhd
|
- Compressive Strength Test
|
Balagon, Indonesia
2018
|
- OAG Offshore Pipeline Service Sdn Bhd
|
- Compressive Strength Test
- Water Absorption Test
|
WHB Project FEED (BDEP), Lumut, Negera Brunei
2017
|
|
|
Al-Tour
2017
|
- OAG International (Labuan) Ltd.
|
- Compressive Strength Test
|
Hail Development Project, Abu Dhabi
2016
|
- OAG International (Labuan) Ltd.
|
- Compressive Strength Test
|
Mumbai-High South Redevelopment Phase 3, India
2016
|
- OAG Offshore Pipeline Service Sdn Bhd
|
- Compressive Strength Test
|
670MW Banten Coal Fired Power Plant, Indonesia
2016
|
- PT. The Second Construction Engineering Third Engineering Bureau
|
|
Wuhan Shangri-La Hotel Phase 2 Extension, China
2016
|
- I Tech Project Management Sdn. Bhd.
|
|
Brunei Temburong Bridge Project Package CC2 – Marine Viaducts, Brunei Darussalam
2016 – 2018
|
- Daelim Industrial
- Teca (B) Sdn Bhd
- UEM Builders Sdn Bhd
|
- Aggregate Test
- Modulus of Elasticity Test
- PC Strand Test
|
Banten Power Project, Indonesia
2015
|
- Harbin Electric International (HEI)
- China State Construction Engineering Corporation (CSCEC)
|
- Core Test (Structure: Chimney)
|
Modernization of Brunei International Airport Terminal, Brunei Darussalam
2014
|
|
- Covermeter Survey
- Concrete Test
- Steel Test
- UPV Test
|